Planning poker

Planning poker is method for estimating the effort required to complete tasks. This is a consensus method typically used for assigning story points to user stories during the initiation of a Scrum project. Each participant has a deck of planning cards which are based on a modified Fibonacci set with a couple of additional cards;

The numeric cards represent story points, the question mark represents an unknown value, the infinity symbol represents a never-ending task and the pause card is to signify a break is desired. One user story that each member can relate to is found and assigned a story point baseline value. After this each user story is assigned a relative value by each participant playing a card face down. If on revealing the cards there is a consensus then that is the assigned value of story points. If there is a difference in estimation then a facilitated discussion or quick SysCon will lead to a consensus or best compromise.

 


 

Example: Scrum master X and developers A, B and C get together to do planning poker;

A: I can relate to 'As a store coordinator I want to comment on a post on the wall of my store.' and would like to use this as a base-line. Do you have any resistance to that?

B and C: No, that's fine.

A, B and C play a round, result: 2, 3, 8

X: There's a difference in results. Remember this is just to set the base-line and that these points don't represent objective units of time! Let's find a solution that everyone can use to estimate with. Would you all be happy to call this a 5?

A, B and C agree.

X: OK, now each of you can divide the number of hours you think this task would take you by 5 to get the value of one story point for you. Remember this value for estimating the remaining cards.

B: OK, next user story: "As a user I want to make a request on the item page for the item so that the system knows that I am interested in that item."

A, B and C play a round, result: 5, 13, 13

C: I played the 5 - I don't think this would much longer than the baseline use story.

A: Have you considered the implications this has across the whole stack?

C: Hmm, now you mention it I can see it taking at least twice as long - I change my card to 13.

X: OK, so we'll assign that card 13 points.

... etc

 

 

meta

Type: event, tool
Phase:
Planning
Works well with:
Incompatible with:
Part of:
yunity Scrum
Requires:
Planing poker cards
Made easier with: A facilitator



To the extent possible under law, the yunity wiki contributors have waived all copyright and related or neighboring rights to the content of the yunity wiki. More information...


You have an account but can't edit or create pages? Write us in the open chatroom or in our yunity Slack!