11.8.2017
→ we need a roof that is good for a year
how to deals and work with DDT wood. Take it out?
some new cracks
everytime it rains someone goes to the roof (doug says he will) look, mark if new cracks are there, if there are fix them
the smallest ones (two drops in a heavy rain) doesn’t have to be
two applications of the current paste, get material for burning
matthias finds out what the best kind of bitumen for that purpose would be
we are doing patchwork
we need to stop water from coming into the walls
increase visualisation → remove some wood → where to store it? Test it. Can it be reused? Probably most is treated
Roof timeline
For a good sustainable roof:
Until February
finished thinking how do we want to do the roof structurally, different shape? Material? Exchange wood? funding, connect to people who know about roofs and have experience (architects, statics)
beams and roof, DDT testing
February get in contact with people who would do the work
May/June start construction work (need a week where it’s not raining)
funding for exchanging roofs? From the state