Roof- measure for now and rough timeplan

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

Version 1 Current »

11.8.2017


we need a roof that is good for a year

how to deals and work with DDT wood. Take it out?

some new cracks

everytime it rains someone goes to the roof (doug says he will) look, mark if new cracks are there, if there are fix them

the smallest ones (two drops in a heavy rain) doesn’t have to be

two applications of the current paste, get material for burning

matthias finds out what the best kind of bitumen for that purpose would be

we are doing patchwork

we need to stop water from coming into the walls

increase visualisation → remove some wood → where to store it? Test it. Can it be reused? Probably most is treated


Roof timeline

For a good sustainable roof:

Until February

finished thinking how do we want to do the roof structurally, different shape? Material? Exchange wood? funding, connect to people who know about roofs and have experience (architects, statics)
beams and roof, DDT testing

February get in contact with people who would do the work

May/June start construction work (need a week where it’s not raining)

funding for exchanging roofs? From the state